| dc.description.abstract | The	construction	resources	are	most	
necessary	for	 running	 the	 construction	 projects	
consistently	 up	 to	 their	 finishing	 stage	 and	
construction	 resource	 planning	 and	
management	compulsory	to	ensure	project	goal	
in	any	project	that	the	on	time	handover	within
budget.	 The	 whole	 construction	 industry	 of	 Sri	
Lanka	 was	 affected	 by	 advent	 of	 COVID-19	
pandemic	 outbreak	 and	 the	 most	 construction	
projects	 had	 to	 face	 the	 difficulties	 of	 effective	
resources	management.	 The	 research	 approach	
has	 been	 taken	 in	 to	 investigate	 the	 resource	
finding	 issues	 that	 arisen	 with	 COVID-19	
pandemic	in	four	highway	construction	projects	
which	selected	from	four	provinces	in	Sri	Lanka.	
The	 study	 also	focused	 to	identify	 the	 effects	 to	
projects'	 delay,	 cost	 and	 quality.	 Through	 the	
literature	 review	 around	 topic	 background,	
seventeen	resource	finding	issues	related	factors	
were	 identified	 under	 three	 categories	 that	
human,	 material	 and	 financial.	 Then,	 the	
importance	 level	 of	 identified	 factors	 were	
justified	 to	 this	 particular	 study	 through	 the	
responses	 gathered	 using	 questionnaire	 survey.	
The	 responses	 were	 taken	 from	 construction	
professionals	 (project	 managers,	 planning	
engineers,	 construction	 managers,	 QA/QC	
engineers,	quantity	surveyors	and	site	engineers)	
who	 selected	 according	 to the	 researcher	
judgement	 from	 four	 contractor	 firms.	 Then	
factors	were	analyzed	and	ranked	using	Relative	
Importance	Index	(RII)	and	descriptive	statistics,	
utilizing	 Excel	 and	 SPSS	 software.	 The	 results	
presented	 that	 the	 whole	 factors	 perfectly	
affected to	 resource	 finding	 issues	 and	 were	
discussed	with	qualitative	findings	to	show	their	
effects	 on	 projects’	 delay,	 cost	 and	 quality.	
Finally,	 concluded	 the	 identified	 effective	
solutions for	 continuing	 highway	 construction	
projects	during	COVID-19	pandemic period | en_US |